The Enron Saga

            




<<Previous Page

A Tripp

The MSEB's inability to pay DPC was rapidly emerging as a threat to the viability of phase II of the project, which involved a generating capacity of 1, 400 MW and an LNG terminal of 5 million tons. There was an increasing possibility that the dispute over phase I might end up in international arbitration, if MSEB failed to pay up and the state government refused to bail out the ailing MSEB. The PPA had provisions for arbitration in case a dispute could not be resolved through negotiations. The DPC and the MSEB would have to work out alternative options, as the project was unviable in its present form. Said Kirith Parikh, former director, Indira Gandhi Institute of Development Research (IGIDR), "Yes, the power from Enron is currently expensive, but a solution needs to be worked. Throwing the Enron project into the sea is not an option."

Business Ethics Case Studies | Case Study in Management, Operations, Strategies, Business Ethics, Case Studies

or
Business Ethics Case Studies | Case Study in Management, Operations, Strategies, Business Ethics, Case Studies

or
PayPal (7 USD)

1. One option could be allowing the DPC to sell power to other states. That would keep the plant running at full capacity and keep the per unit cost low. But the Electricity Act did not allow any trading of power, and prevented the DPC from selling power to anyone but the MSEB. Implementing this would mean a change in the Indian Laws. On February 8, 2001, a high level tripartite meeting of DPC, GoM and MSEB agreed to explore the possibility of selling power from Dabhol to other parties. DPC was of the opinion that up to 700 MW could be sent to other states through the existing transmission systems.

2. There were reports of efforts to sell DPC's power to Karnataka. But according to power experts, the transmission lines between the west and the southern grid were too weak to permit a sale of more than 380 MW of power to Karnataka. The other states in the western grid were Gujarat and Madhya Pradesh. Of these, Gujarat was fully occupied with the consequences of the earthquake and was not in a position to absorb DPC's current capacity of 740 MW, let alone its expanded capacity of 2,100 MW by the end of 2001. Madhya Pradesh's State Electricity Board was in even worse shape than Maharashtra's.

3. In early 2001, GoM appealed to the GoI to bail it out by getting NTPC to pick up equity stake in DPC . If MSEB or NTPC were to take another 20% stake in DPC, they would gain control of the project. This would also allow them to renegotiate the PPA. In early 2001, Enron made it clear that it was no longer interested in power projects in India and its focus would be broadband and data centers. Accepting this proposal would allow Enron to walk away from DPC.

4. The third option would be renegotiation of the contract. But Enron refused to consider that. If Enron agreed to renegotiation then one possibility was that the tariff could become back-ended instead of being front-ended. Under the renegotiated contract, a risk management mechanism against the price of oil could also be worked out. The average price of fuel could be agreed upon in advance and any movement away from that price could be negotiated into the next year's bill.

Next Page>>

Advertisement...

top