The Enron Saga

            




<<Previous Page

Exhibits

Exhibit II

Cogentrix Power Project

In 1992, the Karnataka State Electricity Board (KSEB) signed a Power Purchase Agreement for a 1000 MW coal-fired power plant at Mangalore with an American company, Cogentrix Energy Inc. The coal was to be imported. KSEB promised to purchase power from Cogentrix for a period of 30 years. At the price agreed upon, KSEB would pay Cogentrix about Rs. 2000 crore in the first year that the plant was operational. The total contract was valued at Rs. 75,000 crore. KSEB faced a worse situation than MSEB, as it had to pay nearly 80% of its total revenue for a 25% increase in capacity. The state cabinet issued an office order authorizing the state government to enter into MoUs for 250 MW projects in Mangalore and Bangalore. In July 1992, in violation of Government of Karnataka's (GoK's) order, the MoUs were signed with Cogentrix for two 500 MW projects. Also, in violation of its own orders, the GoK, in the MoU with Cogentrix, allowed the company to bring in any partners they wished.

In 1992, Cogentrix was a very small company. Its total paid up equity was less than Rs. 45 lakhs. Again, at the time of coming to India, its debt equity ratio was 19.2: 1. The company had no international experience and had never undertaken any project of more than 250 MW. Thus, it seemed that the company could not under any circumstances be in a position to execute the project. In February 1993, a committee of secretaries of the state government recommended the approval of the project. In March 1993, a government order permitted Cogentrix to sell power directly to Industrial Units at mutually negotiated rates. Subsequently, this order was overturned and the government asked KSEB to buy all power from Cogentrix.  Thereafter, the plant at Bangalore was cancelled and the plant at Mangalore was allowed to double its capacity to 1000 MW. With the shift of location, a new set of problems emerged. Since all the power generated in Mangalore locally was not required, the power had to be transmitted to Bangalore. This transmission of electricity from Mangalore to Bangalore required new transmission lines, which called for an additional investment of Rs. 750 crore. In addition, the Electricity Board would incur transmission and distribution loses to the extent of upto 20% for the transmission of this power to Bangalore.

Despite the problems the project continued. The state government was to sign a PPA with Cogentrix. In January 1994, the central government made it a pre condition that the PPA be vetted by independent experts if it has to issue a counter guarantee. A team of experts from India (Tata Energy Research Institute (TERI), together with American and German firms, issued a report that was severely critical of the PPA. They commented that the PPA was one sided, and that the capital cost of the plant was too high. Cogentrix was either getting outdated equipment, or if it were using state of the art equipment, it stood to gain about Rs. 70 crore a year as hidden profits on this single count. Again, the cushioning in the capital cost and other such factors would add very substantially to the company's profits, at the expense of the exchequer. In August 1994, a PPA was signed by the KSEB with the Mangalore Power Corporation (MPC). Cogentrix was the sole promoter of this company. In January 1995, the MPC submitted a techno-economic feasibility report. In August 1995, a company from Hong Kong, Chinalight and Power was brought in as a "co-sponsor" in the project. The MoU entered between the two parties was not disclosed. The balance sheet of the MPC for the period 1995-96 did not show any expenses incurred in India or abroad. However, between 1992-96, the balance sheet of Cogentrix showed that approximately Rs. 175 crore had been incurred as "developmental expenses" on the Indian Project. In 1998, a public interest litigation was filed in the Karnataka High Court alleging payment of kickbacks. In response to the petition, a division bench of the High Court issued a directive for a CBI enquiry into the matter. However, a Supreme Court Bench stayed this order of the Karnataka High Court, without assigning any reason. In December 1999, Cogentrix announced that it would withdraw from the project. Among the reasons given by Cogentrix for opting out of the project was the public interest litigation which was pending in the Supreme Court.   

Source: ICMR

 

Business Ethics Case Studies | Case Study in Management, Operations, Strategies, Business Ethics, Case Studies

or
Business Ethics Case Studies | Case Study in Management, Operations, Strategies, Business Ethics, Case Studies

or
PayPal (7 USD)

Advertisement...

top