The Enron Saga

            




<<Previous Page

The Power Factor

The MoU between Enron and MSEB was signed prior to the examination of the terms and conditions and implication of the project. Among the parameters that should have been examined were the capital cost of the plant (on which the price of electricity depends), the type of fuel to be used, the location of the plant etc. An autonomous organization, the Central Electricity Authority (CEA) was supposed to examine these aspects.

Business Ethics Case Studies | Case Study in Management, Operations, Strategies, Business Ethics, Case Studies

or
Business Ethics Case Studies | Case Study in Management, Operations, Strategies, Business Ethics, Case Studies

or
PayPal (7 USD)

In July 1992, the CEA examined the MoU and pointed out that the price agreed on was a departure from the existing norms and parameters notified by the Government. It also pointed out that "denominating the price in US dollars was also a departure from the existing norms." According to the CEA, the price that had been agreed upon was "considered high."

In July 1992, the Government of India asked Enron to submit a break-up of the project costs and the return on equity that was assumed. Enron wrote back stating, We advice you against auditing project costs and predetermining return on equity." Having signed the MoU, Enron now wanted to rush through the PPA . Since the project was to be examined as per the provisions of law, Enron's lawyer, Adrian Montague carried out an analysis of Indian laws. In September 1992, a note called "The Problems Concerning the Application of the Indian Electricity Acts" was sent to the Secretary of Power, GoI highlighting the problems that the provisions in these Acts raised for the Dabhol power project.

The problems identified by Enron were, "Power of MSEB and CEA to regulate DPC activities"; that the DPC would "have to follow all directions of MSEB" and the tariff regulations published by the government. The tariff regulations were found by Enron to be "incompatible with the financial structure of a power station." The Electricity (Supply) Act laid down certain duties of a generating company. These included operating and maintaining the power station in the most efficient and economical manner. Enron was concerned about the consequences of a breach of this provision. It wanted to know who would enforce these provisions.

The last problem identified by Enron was that the DPC like any other limited company would be required to abide by the provisions of the Companies Act. Enron had to furnish to the CEA, account, statistics, returns of other information relating to the generation, supply and use of electricity.

In September 1992, after joint discussions between Enron, the MSEB and the GoM, the Chairman of MSEB wrote to the GoI stating that, "Public and judicial scrutiny of business policy and decisions as per the Act will not be acceptable by a company like DPC".

To facilitate the signing of the PPA, the law had mandated that the price of power and technical aspects of the project be cleared by the CEA. However, Enron made it clear that it did not want to have the price it had set down examined by anyone. Enron was trying to sign the agreement with the MSEB without the necessary "techno-economic" clearance of the CEA . The MSEB also insisted that it be allowed to sign the agreement with Enron first and seek clearance later. Meanwhile, in March 1993, Enron informed the GoI that since it was in no position to procure gas supplies, it would split the project into two phases .

Next Page>>

Advertisement...

top